Description: 555 kw roof-mounted system
SHR Role: Partner/Consultant
- After repeated failure by other developers, SHR obtained long-term financing, ending a lengthy delay in starting the project
- Worked closely with contractors to finalize design modifications
- Construction began October 2014, expect completion Spring 2015 (Severe early onset of winter weather delayed construction.)
- Contractor/Developer praises SHR professionalism in closing the deal